The budget cost for activity a is $100. The duration for a is 4 days. The budget cost work scheduled on day 3 is ______. If only 50% of work is completed on day 3, What is the budget cost work performed?

Respuesta :

Otras preguntas

2/3 x 1/4 in simplest form
rounding - 8.238; tenths 3.666; tenths 4.47; ones 10.86; ones 3.299; hundredths 20.687; hundredths 2.3654; thousandths 69.0678; thousandths 5.58214; hund
What present day countries control territory that was controlled by the Seleucid empire?
Calculate the discriminant.x2 – 2x + 4 = 0      20      12    –12      0
DO you know a animal with the name that starts with the letter n?
how does geography affect Philippines history?
which are the numbers that are common multiples of 6 and 8.12 18 24 30 40 48
how does geography affect Philippines history?
How much can a glass of water hold?A. 1 gallonB. 1 cupC. 1 quart D. fluid ounce (answer now please on a test)
Ship that revolutionized travel during the age of exploration