Using the PERT estimate, calculate the estimated duration of an activity given:
Optimistic Estimate = 21 days
Pessimistic Estimate = 110 days
Most Likely Estimate = 55 days
a) 62.5 days
b) 74 days
c) 65 days
d) 68.5 days

Respuesta :

Otras preguntas

Mollusks in class bivalvia a. have two shells. b. lack a "head." c. do not have a radula. d. all of the above
How is the Declaration of Independence connected to John Locke’s ideas on natural rights?
Simplify square root of 324
A chain fits tightly around two gears as shown. What is the radius of the smaller gear? Round your answer to the nearest tenth. 1.6 in. 9.6 in. 12.0 in. 6.4 in
Suppose that 56% of people own dogs. if you pick two people at random, what is the probability that they both own a dog?
Complete the chart comparing the powers and responsibilities of the three branches of the federal government. then write a short analytical paragraph comparing
Please help me find the length!!
how is penicillin used? A. to kill bacteria that cause disease B. to kill protests that cause disease C. to make bread rise D. to make cheese
discuss the characteristics of relations that make them different from ordinary tables and files
Correct definition of urban center