A project has five activities as follows:
Activity: A, B, C, D, E
Preceding Activity: -, -, B, C, B
Duration (Days): 4, 8, 5, 9, 5
a) Find critical path using EST's / LST's
b) Calculate the floats of the network.

Respuesta :

Otras preguntas

Which musical style has Equatorial Guinea adopted as a popular mainstream style? makossa gospel kizomba orchestral
Write an equation for a parabola that has a vertex (1, 2) and passes through the point (3, -6).
Asset cost $35,000Prepaid Insurance $5,000Maintenance costs $3,000Accumulated Depreciation $10,000Book
Tre and Hector want to calculate the maximum possible throw at this field. They calculate that the farthest point on the field would be the center fielder stan
Point T Is the incenter of PQR.Point T is the point of concurrency of the angle bisector. Find ST.
Evaluate (f *g)(x) if f(x) = 2x^2 and g(x) = 3x – 2.
720 companies 8 companies win what is the probability
anong bansa ang tumiwalag sa liga ng mga bansa noong 1933​
Select the correct answer. Allan is manager of the software. His team has compiled various design documents prior to starting the development of the software. A
Plz help me asap !!!