10 road workers take 5 days to complete a road repair, working 2 hours a day. How many days would it take 2 people working 5 hours a day to finish a repair?

Respuesta :

gusogrady
gusogrady gusogrady
  • 13-01-2020
10 days, 10 workers, 5 days, 2 hours a day= 100 total hours of work. So 2 people working 5 hours a day is 10 hours total. 10 x 10 is 100 so 10 days
Answer Link

Otras preguntas

what does the limbic system do
Tp-21 gasoline and propane fumes are most likely to accumulate in what part of the boat?
It is possible for an organism to inherit a gene with two dominant alleles. What is a gene with two dominant alleles that are expressed at the same time?
The equation x^2-6x+2=29 has two solutions, a and b, with a≥b. What is the value of 2a-3b?
Describe qualitatively how the tm for a double-stranded dna depends on its nucleotide composition
Which is faster rate? 3 Laps in 5 minutes or 4 laps in 7 minutes?
$21000 at 13.6% compounded quarterly for 4 years
in simest form whats the ratio of 4 days to 2 weeks
Which of the following side lengths could form a triangle
5.1 Describe unsafe practices that may effect the well being of individuals