It takes 20 men 60 days to complete a building work.How many days longer will It take 15 men, assuming they work all work at the same rate?

Respuesta :

maempress
maempress maempress
  • 13-07-2020

Answer:

80days

Step-by-step explanation:

20m=60days

15m(will take more days)

20÷15×60 = 80 days

Answer Link

Otras preguntas

How do you multiply to find an equivalent fraction of. 3/10
How many quarts are in 2 and 3/4 of a gallon
what is 33 1/2 of 24 and 37 1/2 of 80 and finally, what is 66 2/3 of 45
what is 33 1/2 of 24 and 37 1/2 of 80 and finally, what is 66 2/3 of 45
Which of the following prefixes is best for measuring large quantities like the mass of a person? milli kilo deci deca
I Am A Number That Is Double The Product Of 2 And 7. One Of My Factors Is 7 What Is My Other factor
What does ayudando mean?
What does ayudando mean?
What is a good sentence for the word orbit?
Which statement is always true about a trapezoid?1.it has 2 congruent sides.2. It has 2 right angles3. It has no congruent angles4. It has exactly 2 parallel si