If 5 workers complete one task in 7 days, then how many days will 7 workers take to complete the same task?

Respuesta :

liftec liftec
  • 14-11-2020

Answer: 5 days

Step-by-step explanation:

5*7=35 - means the total amount of the days to complete the job by 1 worker is 35 days

So 7 workers can do this job in

35:7=5 days

Answer Link

Otras preguntas

I need help with the two in the picture please.
When is it preferable to use a plastic volumetric flask instead of a more accurate glass flask?
Can the perimeter of a rectangle be any integer value
WILL GIVE BRAINLIEST TO BEST ANSWER- DUE TODAY Use the quadratic formula to solve x^2-4x+3, Show your work. Then describe the solution.
PLEASE HELP MEEEEEEEEEEEEEEEEEEEEEEEEE
5. Match the vocabulary word to the correct definition. 1. Objective image 2. Organic shapes 3. Principles of art 4. Lines 5. Nonobjective images a
When people do not own the resources they use, they tend to do what?
Nitai, who is single and has no dependents, was planning on spending the weekend repairing his car. On friday, nitai's employer called and offered him $500 in o
How did the Supreme Court defined the role of the federal government in murbury v. Madison (1803) and McCulloch v. Maryland (1819)
yo siempre ____ la verdad