if 9 men can complete a job in 4 days, how long will 8 men take to complete the same job, assuming that all the men are working at the same rate?

Respuesta :

irspow
irspow irspow
  • 12-03-2021

Answer:

Step-by-step explanation:

8t=9(4)

8t=36

t=4.5

So it will take 4.5 days for 8 men to finish the job.

Answer Link

Otras preguntas

Which state is farther North ,Washington or Oregon ?
How can fertility rates affect the use of scarce resources?
c=a(w/150) solve for w
steve has 500 more marbles than richard at first. he gives 300 marbles to richard. who has more marbles now, and by how many?
Help me to understand this: V=lwh; l=14, w=8, h=3 (volume of a rectangular box)
The ratio of boys to girls in a class is 5 to 6 which is an equivalent. Ratio
Which occurs on earth more often? Physical or chemical changes?
Jake's dad bought a lawnmower for $648.52. Which shows this amount in expanded form ? A: (6 X100) + ( 4x10) + (8x1) +(5 x 10) + (2 x 1) B: (6x100) + (8x1) + (4x
The ratio of boys to girls in a class is 5 to 6 which is an equivalent. Ratio
84:36=_____:3 Find the missing term of each pair of equivalent ratios