A project will take 720 person-days to complete. How many days will it take to complete the project if 5 people work on it?

Respuesta :

burgkann burgkann
  • 13-12-2021
720/5= 144, it will take 144 days for 5 people to finish the project.
Answer Link

Otras preguntas

what are the 4 steps of the writing process
1. a government run by the people who live under it. People rule either directly through meetings that all may attend, or indirectly through the election of rep
solve log3(x+4)=log3(1-x) please
for the month of March Cassie plans to vacuum her floor every fourth day and clean her bathroom every 7th day if she begins this March 1st on what day of the mo
What option best describes the concept of globalization ?
Polygon LMNP slides 5 units right and 4 units down on the coordinate plane. If the original measure of angle M was 50 degrees, what is the measure of angle M′?
Hello! Can you teach me how to solve this?
How do i graph the original triangle?
Can someone please help me
I’m lost can someone please tell me the answer?