It takes 6 workers 8 hours to tile a hall . How long will it take 4 workers to complete the same job

Respuesta :

icandoitjwk icandoitjwk
  • 15-01-2022
6w=8
2w=8/3

So
4w=8/3x2
4w=16/3
Answer Link

Otras preguntas

The distance between Earth and its moon is 3.84 × 108 meters. Earth’s mass is m = 5.9742 × 1024 kilograms and the mass of the moon is 7.36 × 1022 kilograms. Wh
When did the baby boom take place in the United States?
what is 36/63 in simplest form?
write 103,727,495 in expanded form
A drawer has 5 red socks and 5 socks.  If 3 drawn what is the probability that they are a match?
what are the basics for triganometrey
In an 8.00 km race, one runner runs at a steady 11.0 km/h and other runs at 14.8 km/h. How far from the finish line is the slower runner when the fast runner fi
In August, the Simons water bill was $48. In September, it was15% lower. What was the Simons water bill in Septemper? I don't get it because I got 7.2. Please h
For a chemical reaction it is usually found that the reaction rate is faster at higher temperature. The rate increases because (a) the concentrations of reacta
My problem says"Write two ratios that are equivalent to 1:1