  • Mathematics
contestada

Spencer can do a piece of work in 20 days and Toby in 25 days. They began to work together.
But Spencer leaves after some days. Toby finish the remaining work in 11 days. After how many
days did Spencer leave?
Show work

Respuesta :

2942863
2942863 2942863
  • 15-03-2022

Answer: spencer left after 14 days

Step-by-step explanation:

Answer Link

Otras preguntas

What is $2.50 times 7?
What number goes into 104 and 60?
How are mixtures and solutions alike
Salinity is a measure of which of the following in water? a. carbon dioxide b. oxygen c. dissolved salts d. sand
Rocks carried by the river smash together and break into smaller pieces. This process is called _____. 1)abrasion 2)attrition 3)suspension 4)mass wasting
Write a description of how the animal cell transports water?
what technological improvement did the assembly line bring? a) greater productivity b) improved communication c) reducyion of human workload d) faster transport
Hamburger sells for 3 pounds for $6. If Samantha buys 10 pounds of hamburger, how much will she pay?
What is the distributive property of 56 divided by 4
What is 6.6 repeating as a fraction