If it takes 10 men 4 hours to repair a barn, how long will it take 8 men to complete the task?

Respuesta :

RickyChen
RickyChen RickyChen
  • 13-07-2017
Let's assume it takes x hours.

People will be inversely related to hours, which makes more sense, sorry for my previous wrong answer.

Calculate the relationship: k = 10*4 = 40

So, 8x = 40, x = 5


Answer Link

Otras preguntas

Teenagers were asked what type of book they prefer to read. There were 18 teenagers who prefer e-books and 7 teenagers who prefer paperback or hardcover books.
B) Desiree could have taken her baby and returned to her mother's home. Why did she choose death rather than the protection of her family? I need 500 words
Do a close reading of George Harris’s letter and explain the position that it takes on what it means to be a freed slave in America. Use specific evidence. Your
I have a surious question What causes a concussion?
What is the x-value of the solution to the system of equations? 5x + 4y = 8 2x - 3y = 17 -3 -2 4 5
Which u. S. State is home to the longest known cave system in the world?.
255,250,245,... Find the 40th term.
Who was Tamerlane, and what is he known for?
By lubricating the pulley, the work needed was decreased from 50 J down to 44 J. The output work of the pulley remained 40 J. The efficiency of the pulley AFTER
u 10. Match the benefit of full synthetic oll with engine conditions: Engines are cold at start-up and not while running. A) Synthetic has greater resistance to