Labor rate = $7.50 per hour Labor time = 6.5 hours Retail price of parts = $0 Total job cost = $82.00 Overhead rate?

Respuesta :

Aliwohaish12
Aliwohaish12 Aliwohaish12
  • 13-07-2017
Total cost job=
Retail price of parts+labor cost+manufacturing overhead

Total cost job 82

Retail price of parts 0

Labor cost=7.5×6.5=48.75

Manufacturing overhead ?

82=0+48.75+?

?=82−48.75

?=33.25

Manufacturing overhead is 33.25

Now find manufacturing overhead rate from the cost of labor
33.25÷48.75=0.682×100=68.2%

The answer 68.2%




Answer Link

Otras preguntas

Find the domain and range of the INVERSE of the given function. Square root x-3
I want to know how many bricks and cement it would take to build the following brick wall: the bricks are 16 inches by 8 inches, and the wall would measure 6 ft
A number added to itself twelve times is five more than twice the number. What is the number?
what is the least number that must be added to 2000so that the sum is devided exactly by 10,12,16 and 18
(2+7i)(2-7i)= ==========
How much would $600 invested at 8% interest compounded continuously be worth after 3 years? Round your answer to the nearest cent.
A mixture of 30 pounds of candy sells for $1.10 a pound. The mixture consists of chocolates worth $1.50 a pound and chocolates worth 90¢ a pound. How many pound
Find three arithmetic means between -2 and 12.
I need help here please..! I took a picture of the Multi -Step equations..!
'I am the largest 5-digit number you can make that has all odd digits. My ten thousands digit is thrice my ones digit. My thousands digit is two more than my hu