sí 8 trabajadores tardan 5 días en hacer una obra, cuánto tardarán si son 16 trabajadores, Y si son 4 trabajadores. proporcionalidad

Respuesta :

amendocrr amendocrr
  • 14-04-2018
si son 16 trabajadores serian 10 días porque 8 es la mitad de 16 y si fueran 4 trabajadores seria 2.5 días 

Answer Link

Otras preguntas

If P = (-3, -2) and Q = (1 , 6) are the endpoints of the diameter of a circle, find the equation of the circle. (x - [?])2 + (y - [ ])2 = [ ]
Evaluate the following function: Show all work! h(x)=3x²+2-2x, Find h(-2)​
Which paragraph best supports that claim that cell phone use is on the rise? paragraph 2 paragraph 4 paragraph 3 paragraph 5
Another assignment I'm hopelessly stuck on :(
Please help quick I will give 100 points REAL ANSWERS ONLYWhat Do I Have To Do?In this lesson, you learned about the city-states of Athens and Sparta. Suppose t
In three to five sentences, identify two components of the control subsystem of a vehicle, and use them why driving can be hazardous when the control subsystem
Help! Help! Help! Help!
work out one quarter $80? please help me​
According to the graph, during which time interval are the particles in the air slowing down? A. 3:00 p.m. to 6:00 p.m. B. 6:00 p.m. to 12:00 a.m. C. 3:00 a.m.
I need some math help please